Electrical Contracting for a 12 MW Data Center
A 12 MW data center was built in the Helsinki metropolitan area. Terawatt delivered full electrical scope for the facility.
- Year completed: 2024-2025
- Location: Helsinki metropolitan area
- Size: 12 MW
- Property type: Data Center
- Main contractor: Undisclosed
A Significant project for Terawatt
Terawatt began preparing its bid for the data center’s electrical works in 2024. Several members of the main contractor’s team had worked with Terawatt on previous projects and valued the collaboration. Following negotiations, the main contractor awarded Terawatt the electrical contract, and work began in summer 2024.
Terawatt was responsible for electrical scope:
- MV Distribution
- LV Distribution
- General and Emergency Lighting
- General Service Power
- Mechanical Plant Service Power
- Fire Detection and Alarm
- Access Control, Intruder and CCTV
- Earthing and Bonding
- Lightning Protection System
- Data Centre Halls Power Distribution
- BMS Cabling
- Full busbar installation

Reliable Power Distribution on a Tight Schedule
Data center construction involves substantial power requirements and a broader scope of electrical work than a typical commercial building project. Before work began, Terawatt reviewed the electrical plans in detail and assembled a team led by an experienced project manager, supported by lead electricians and site supervisors. This preparation helped the team get work underway smoothly.
Two priorities guided the electrical installation:
- Quality. Reliable power distribution depends on consistent workmanship throughout the system. Every connection, cable termination, and fixing was installed with care.
- Schedule. The team planned and coordinated the electrical work around a demanding construction schedule to support the data center’s planned start of operations.
Open collaboration enabled success
The workload of the project increased significantly as it progressed, and at its peak, more than 160 electricians and office personnel were working on site, which brought its own challenges. Maintaining an overall view and reviewing design changes for both the client and our own team played a crucial role in a hectic schedule. Overall, the project was successful: the facility was made operational and handed over on time. Close and open cooperation with the main contractor and the client made this success possible.

Looking for an electrical contractor for a data center project?
Get in touch, and let’s go through how we can help!
