As Oy Untuvaisentie 2 Solar Plant
As Oy Untuvaisentie 2 Invests in Its Own Solar PV System
- Year completed: 2025
- Location: Helsinki
- Size: 16 kWp
- Property type: Apartment Building
- Main contractor: Terawatt Oy
Housing Company in Helsinki Embraces Solar Power
The solar PV system generates electricity for the property’s own consumption.
As Oy Untuvaisentie 2 is a housing company dating back to the 1960s that has undergone extensive modernisation over the years.
In 2024, the housing company replaced district heating with a ground-source heat pump system to avoid rising district heating costs. As part of the heating system upgrade, the property’s electrical infrastructure was reinforced, and provision was made for a future solar PV installation by running a higher-capacity cable from the main switchboard in the basement to the roof.
This advance preparation made the installation of the solar PV system considerably more straightforward, as routing a new cable from the attic to the basement would likely have been a labour-intensive task.

Procurement Process
Terawatt prepared a quotation for the solar PV installation and, following negotiations, reached an agreement with the housing company.
The quotation outlined the proposed peak power capacity of the solar PV system (kWp), representing its maximum rated output under standard test conditions, together with an estimate of annual electricity generation.
The proposed equipment, generation monitoring system and mounting arrangements were also reviewed in detail. The quotation included a preliminary layout of the solar panels on the roof, which was to be verified during a separate site visit.

Construction Begins
Once the contract for the solar PV installation had been signed, a site survey was arranged with the housing company. In addition to Terawatt’s site supervisor, the survey was attended by a representative of the mounting system manufacturer and the electrical works supervisor appointed by the housing company. This allowed all parties to establish a shared understanding of the scope of work and the installation arrangements.
During the site survey, the existing main switchboard was inspected, and minor modifications were identified as necessary to connect the solar PV system to the electrical network. It was also agreed that the inverter would be installed in a safe location on the attic floor.
Regarding the positioning of the solar panels, the initial proposal to use the wall of the attic storey was abandoned. This would have altered the building’s external appearance and potentially delayed the project, as the proposed changes would have required consultation with the local building control authority.
The housing company had requested a tight project schedule, so the parties decided not to pursue an option that could introduce additional delays. The site survey also established the lifting locations and confirmed the final layout of the solar panels.

Completed in Just a Couple of Weeks
The solar PV installation progressed smoothly and was completed in approximately two weeks. The solar panels were installed using a mounting system welded to the bitumen roofing membrane. This solution reduces the weight load on the roof while ensuring that the panels remain securely in place, even during severe storms.
The successful delivery of the project was supported by effective collaboration between the housing company, the contractors and the appointed supervisor. The advance site survey enabled the installation works to be carried out in accordance with the supervisor’s requirements from the outset, avoiding unnecessary remedial work. The previously installed supply cable also significantly reduced the scope of the electrical works, making the addition of the solar PV system considerably more straightforward.
The solar PV system has an estimated service life of approximately 30 years. It will generate electricity for the property’s own consumption, including ventilation equipment, lifts and ground-source heat pumps.